Construction continues by most of the trades on the project from brick masons to interior framers to electricians. The floorplan is taking shape throughout the project as the gypsum board is being installed on the interior framing to be followed by taping, mudding and sanding joints with primer and paint. Staff continues to work on the sign program, the theater marquee, a bridge connecting the project with city hall, bleacher installation, furniture and equipment orders for the recreation side. Progress also continues on the lease up as we have two tenants locked-in with a few others with letters of intent in review.